West Broad Street Short Pump Road Improvements: What VDOT’s Route 250 Project Means for Retail Tenants and Owners

VDOT plans a $24.3 million operational overhaul of West Broad Street between I-64 and East Pouncey Tract Road, with construction estimated for fall 2028 to fall 2030. Here is what changes and how to protect a lease or property.

By Traver Vliem · Updated · 6 min read

Part of the guide: Short Pump Retail Space for Lease: A 2026 Guide to West Broad Street Rents, Sites, and Lease Terms

Key takeaways

  • VDOT’s West Broad Street (Route 250) Short Pump Operational Improvement runs from I-64 to East Pouncey Tract Road, carries a $24.3 million estimated cost, and is in design with construction estimated for fall 2028 through fall 2030.
  • The scope reconfigures West Broad’s intersections at Tom Leonard Drive, Brownstone Boulevard, and John Rolfe Parkway, adds a continuous through-right option lane, and separates I-64 merge traffic from left turns at Gathering Place.
  • Other projects overlap the same window, including turn-lane work at Dominion Boulevard and Cox Road (spring 2028 to summer 2029) and the new I-64/North Gayton Road interchange (spring 2028 to winter 2031).
  • Tenants signing now should address construction-period access, signage, co-tenancy, and condemnation in the lease; owners should review the plans against their entrances before VDOT finalizes them.
In this guide
  1. What is the West Broad Street Short Pump operational improvement project?
  2. What else is under construction or planned nearby?
  3. How could the West Broad Street Short Pump road improvements affect retail access?
  4. What lease protections should Short Pump retail tenants ask for?
  5. What should property owners do now?
  6. When is the right time to sign a Short Pump retail lease?
  7. Need help evaluating a site on West Broad Street?

The main West Broad Street Short Pump road improvements project is VDOT’s West Broad Street (Route 250) Short Pump Operational Improvement: a $24.3 million effort to improve traffic flow on Route 250 from I-64 to East Pouncey Tract Road, with construction estimated to run from fall 2028 to fall 2030. It reconfigures the intersections at Tom Leonard Drive, Brownstone Boulevard, and John Rolfe Parkway, which means turning movements into some of the corridor’s busiest shopping centers may change.

For retail tenants and property owners, the practical questions are which entrances are affected, how long construction will disrupt traffic, and what a lease should say about it. This post covers the project details from VDOT’s project page, the related projects around it, and the lease terms worth negotiating. For rents, vacancy, and site formats across the corridor, see our Short Pump retail space for lease guide.

What is the West Broad Street Short Pump operational improvement project?

VDOT describes the project’s goal as improving traffic operations along the West Broad Street corridor between I-64 and East Pouncey Tract Road. According to the project page (last updated September 17, 2026), the scope includes:

  • Flex post delineators separating traffic merging onto West Broad Street from I-64 from traffic trying to turn left at the first intersection, Gathering Place.
  • A continuous through-right option lane for the entire stretch of the corridor.
  • Reconfigured intersections at West Broad Street and Tom Leonard Drive, Brownstone Boulevard, and John Rolfe Parkway.
  • Sidewalk upgrades along the corridor to meet Americans with Disabilities Act standards.

The project is tracked as UPC 123583. VDOT noticed its willingness to hold a public hearing in February 2025 and received no written requests, so no hearing was held. The page does not say whether right-of-way will be acquired from adjoining parcels, and it does not publish lane-by-lane plan sheets, so owners should request the current design from the project manager listed on the page.

On funding, Richmond BizSense reported in April 2024 that Henrico had secured $26 million in state SMART SCALE funding for Broad Street improvements. VDOT’s current estimated cost for this project is $24.3 million. The two figures come from different points in the process, so treat VDOT’s page as the current number and expect estimates to move as design advances.

What else is under construction or planned nearby?

The operational project is one piece of a larger package. VDOT’s Short Pump Area Transportation Improvements study grouped seven proposals, including a partial cloverleaf at the Route 250/I-64 interchange and the Tom Leonard Drive through-cut. Several now have their own schedules:

ProjectScopeEstimated costConstruction (estimated)
West Broad Street (Route 250) Short Pump Operational ImprovementI-64 to East Pouncey Tract Road; Tom Leonard, Brownstone, John Rolfe intersections$24.3 millionFall 2028 to fall 2030
West Broad Street at Dominion Boulevard and Cox RoadAdditional turn lanes and new bus transit facilities$14.1 millionSpring 2028 to summer 2029
I-64 / North Gayton Road interchangeNew diverging diamond interchange, a second route into Short Pump$157.4 million total fundingSpring 2028 to winter 2031
West Broad Street and Short Pump road projects (per VDOT and Henrico Citizen, as of September 2026)

The Dominion Boulevard and Cox Road figures come from VDOT’s project page (UPC 118597, design public hearing held May 8, 2026). The Gayton Road figures come from a September 2026 Henrico Citizen report on regional funding approvals. The takeaway for retail: the corridor is likely to see overlapping work zones from 2028 into 2031.

How could the West Broad Street Short Pump road improvements affect retail access?

Operational projects change how cars move, not just how many lanes there are. Reconfiguring an intersection can shift where drivers can turn left, lengthen or shorten turn bays, or close a median opening. A center that relies on a left turn from westbound West Broad could gain or lose that movement. A through-cut or lane conversion can change how easily drivers reach a right-in entrance.

Over the long term, the aim is less congestion. For most centers that is good news, since gridlock near the I-64 interchange discourages shopping trips. During construction, expect lane shifts, reduced speeds, and some temporary entrance changes. Restaurants and convenience users that depend on quick in-and-out trips feel this first.

What lease protections should Short Pump retail tenants ask for?

Landlords do not control VDOT’s work, and most standard leases put the risk of public road changes on the tenant. With a known project on the calendar, it is reasonable to ask for specific protections:

  1. 1Access covenant — the landlord agrees to keep the center’s existing curb cuts and internal drive aisles open, or to provide a reasonable substitute, and not to agree to access changes without notice to tenants.
  2. 2Construction-period relief — rent abatement or a reduction if a named entrance is closed, or customer access is materially impaired, for more than a set number of consecutive days.
  3. 3Temporary signage rights — permission for “open during construction” and wayfinding signs, subject to county sign rules.
  4. 4Co-tenancy — relief if the anchor that drives your traffic closes, including if it closes during the construction period.
  5. 5Condemnation clause — spells out what happens if VDOT acquires part of the property (parking, landscaping, an entrance), including termination rights if the taking materially harms your premises or access, and how any award is split.
  6. 6Timing flexibility — a delivery or opening date that allows for a construction start, or an early-termination right tied to access loss.

Have a real estate attorney draft the language. The value of these clauses depends on specific triggers and definitions, and landlords in a market this tight will push back on broad versions.

What should property owners do now?

Owners should compare the design to their entrances, parking fields, and pylon signs, and raise concerns with VDOT while the project is still in design. If any land is needed, Virginia’s eminent domain statute, Code of Virginia § 25.1-230.1, requires the body determining just compensation to include loss in market value of the remaining property from lost access, and, if strict conditions are met, lost profits for a business on the property. Whether a given change qualifies is a legal question for an eminent domain attorney, not a broker.

Owners also need to plan leasing around the project. Tenants who know about the project will ask for the protections above. Being ready with clear answers and realistic concessions will close deals faster than stonewalling.

When is the right time to sign a Short Pump retail lease?

Waiting until the roads are finished is rarely practical. Short Pump posted 0.7% retail vacancy in Q2 2026, and good space does not sit empty for years. A better approach is to sign with the project in view. Negotiate the clauses above, time your opening so the business is established before construction peaks, or plan a later opening to avoid the worst of it. A lease starting now with a five- or ten-year term will run through the construction window either way, so the terms matter more than the start date.

For the broader picture on rents, formats, and lease terms, go back to our Short Pump retail space for lease guide. If you are a restaurant operator, our guide to restaurant space for lease in Short Pump covers the build-out and permitting side.

Need help evaluating a site on West Broad Street?

If you are weighing a location affected by the Route 250 work, I can help you pull the current plans, compare alternatives, and frame the lease terms worth asking for. You can see the services I provide, or get in touch to talk through a specific site.

Frequently asked questions

When will construction start on the West Broad Street project in Short Pump?

VDOT estimates construction will start in fall 2028 and finish in fall 2030. The project was still in design as of September 2026. Schedules on projects this size often shift, so check VDOT’s project page for updates and build some flexibility into any lease or development timeline that depends on these dates.

Which intersections will be reconfigured on West Broad Street?

VDOT lists Tom Leonard Drive, Brownstone Boulevard, and John Rolfe Parkway. The project also adds delineators near Gathering Place, where I-64 merge traffic meets left-turning vehicles. A separate VDOT project adds turn lanes at Dominion Boulevard and Cox Road. Request the plan sheets to see how each change affects a specific entrance.

Can a tenant get rent relief if road construction blocks access?

Only if the lease provides for it. Most standard retail leases do not give relief for public road work. Tenants can negotiate abatement if a named entrance is closed or access is materially impaired for a set period. Attach specific triggers, a defined remedy, and landlord notice duties, and have an attorney draft the language.

Is a property owner compensated if VDOT changes access?

If VDOT acquires property, Virginia law requires just compensation to include lost market value of the remaining property from lost access, and lost profits to a business if strict conditions are met. Not every traffic change is compensable. An eminent domain attorney can advise on a specific parcel.

Sources

  1. VDOT, West Broad Street (Route 250) Short Pump Operational Improvement (UPC 123583)
  2. VDOT, Intersection Improvements on West Broad Street at Dominion Blvd and Cox Rd (UPC 118597)
  3. VDOT, Short Pump Area Transportation Improvements Project
  4. Henrico Citizen, “Funding for new I-64/North Gayton Road ‘diverging diamond’ sets in motion multi-year project” (September 9, 2026)
  5. Richmond BizSense, “Henrico secures some funding, seeks more for Short Pump traffic improvements” (April 25, 2024)
  6. Code of Virginia § 25.1-230.1, Lost access and lost profits
  7. Cushman & Wakefield | Thalhimer, Richmond Retail MarketBeat, Q2 2026

Market figures are cited to the period each source covers and change over time. This guide is general information, not legal, tax, or investment advice.